Bid Book Book2 Olympic Village Construction Schedule For The Olympic Village

# Stage Deadline
1 Choosing the location and determining the total area of the site Completed
2 Initial environmental impact assessment Completed
3 Determining general architectural solutions Completed
4 Preparing and conducting a tender 3-4 quarter of 2005
5 Detailed environmental impact assessment 2006
6 Submitting and approval of the final architectural design 2007-2008
7 Construction works 2009 -2 quarter of 2011
8 Finishing and fit out 3-4 quarter of 2011
9 Inspection and acceptance of the venue 4 quarter of 2011
10 Pre-Olympic preparation works 1 quarter of 2012
11 Testing 1-2 quarter of 2012
12 Opening of the Olympic Village July 2012
13 Olympic to Paralympic transition August 2012