Stage |
Deadline |
1 |
Choosing the location and determining the total area of the site |
Completed |
2 |
Initial environmental impact assessment |
Completed |
3 |
Determining general architectural solutions |
Completed |
4 |
Preparing and conducting a tender |
3-4 quarter of 2005 |
5 |
Detailed environmental impact assessment |
2006 |
6 |
Submitting and approval of the final architectural design |
2007-2008 |
7 |
Construction works |
2009 -2 quarter of 2011 |
8 |
Finishing and fit out |
3-4 quarter of 2011 |
9 |
Inspection and acceptance of the venue |
4 quarter of 2011 |
10 |
Pre-Olympic preparation works |
1 quarter of 2012 |
11 |
Testing |
1-2 quarter of 2012 |
12 |
Opening of the Olympic Village |
July 2012 |
13 |
Olympic to Paralympic transition August |
2012 |